THE CHALLENGE
Existing site was a former movie theater turned parking lot. During excavation it was discovered that the former theater structure had been demolished and buried in the hole of the foundation.

Mat Foundations
Steel Bent Moment Frames
Structural Steel Stair Tower
THE SOLUTION
The Engineer designed a new mat slab that mitigated differential settlement and allowed the project to stay on track.